Internal
Revenue Code Sec. 48 refers to the cost of a
qualifying renewable energy project
“(i) the construction,
reconstruction, or erection of which is completed by the taxpayer, or
(ii)
which
is acquired by the taxpayer if the original use of such property commences with
the taxpayer.”
The tax basis of projects that are
purchased, or constructed under contract for the ultimate user, is the purchase
price or acquisition cost; which, assuming an arm’s-length transaction, will be
equal to fair market value, defined as:
“the estimated amount at which a property might be expected
to exchange between a willing buyer and a willing seller, neither being under
compulsion, each having reasonable knowledge of all relevant
facts.”
Alternatively, self-constructed
projects will have a basis equal to their cost to construct. Qualifying construction cost includes not
only direct labor and materials, but a variety of soft costs including design
and engineering, internally allocated salaries and expenses, insurance,
construction period interest, professional fees, training costs, management
costs, etc.
In both cases, only the tangible
electrical generating equipment included in the qualified facility is eligible
for ITC. Buildings and
structural components are not eligible for ITC, but may be depreciated
separately.
Ability to
Step-Up Basis
The basis of self-constructed
projects can be stepped up from construction cost to fair market value if they
are financed on a tax-oriented basis through a sale/leaseback or partnership
structure. In general, a project’s
basis in a tax-oriented financing structure will be equal to:
(i)
in the
case of a sale/leaseback, the lessor’s acquisition cost of the project,
or
(ii)
in the case of a partnership investment by a tax equity
investor, the sum of the developer’s and equity investor’s tax bases for their
respective partnership interests.
For example, if a developer
constructs a project with a qualifying cost of $100, and sells it to a lessor
(not later than 90 days after it is initially placed in service) for a fair market value of $120 and
leases it back, the basis of the project - for the purpose of determining
investment tax credit and depreciation expense - will be $120. Under the provisions of ARRA, the ITC or
equivalent cash grant can be passed back to the developer/lessee, essentially
providing the developer with 100% financing and a 30% cash grant based on the
$120 fair market value. (The grant is limited to 10% for certain
project categories including qualified microturbine property, combined heat and
power systems, and geothermal heat pump property.)
Alternatively, the developer may
enter into a partnership structure with a tax equity investor. Under a typical flip structure,
the investor’s partnership interest would be less than the value of an undivided
interest in the project for the same initial percentage of ownership, as the
partnership investor would receive a significantly lower proportion of the
project’s back-end cash flows and residual value.
If the tax equity investor pays
$90 for its partnership interest, assuming the same $120 fair market value of
the project, and an initial 99/1 partnership allocation, the developer’s tax
basis would be $25 [(1-$90/$120) x the $100 cost to construct] and the tax
equity investor’s basis would be its $90 purchase price for its partnership
interest. Assuming a 99/1%
allocation ratio, the tax equity investor would be entitled to claim ITC equal
to 99% of the partnership’s $115 tax basis in its assets (assuming all of its
assets were ITC eligible.) Because
of special rules applicable to property contributed to a partnership (which, in
this structure, the developer would be treated as having done), the tax equity
investor’s 99% share of partnership net income could be calculated assuming
depreciation based on the full $120 FMV of the partnership’s assets. Please note that in all cases, total
allowable depreciation expense would be reduced by half of the ITC claimed, or
15% of the project’s original basis.
In comparing the potential advantages of utilizing a lease
or partnership structure to achieve a step-up in basis and tax benefits, a
project owner or developer should consider the associated transaction expense,
structural complexity, and after-tax financing costs of these alternatives
compared with those of debt financing and a cash grant based on actual
construction cost.
In this context, however, the
important issue for developers is that a potentially significant increase in tax
benefits associated with a qualifying renewable energy project may be realized
through a sale/leaseback or partnership structure, vis-à-vis retaining ownership
of a self-constructed project. The potential incremental tax benefits
naturally depend on the difference between a project’s construction cost and its
fair market value.
The determination of construction cost is conceptually
straightforward, although in practice differences in construction management,
financial reporting, and MIS systems may complicate the task of capturing all
costs that may legitimately be included in the tax basis of a self-constructed
project.
In general, “hard” costs would
include land, land improvements, buildings, process construction materials,
controls, the physical machinery and equipment located at the facility, and any
additional support equipment.
However, as noted above, under ARRA only electrical generating equipment
integral to a qualified facility is eligible for ITC. Buildings and
structural components are separately depreciable, but not as components of a
qualifying project.
“Soft” costs can be broken down
into three categories: direct, system, and facility. Direct soft costs are those that can be
applied to a specific hard asset and would include any applicable taxes,
freight, and installation. System
soft costs are those that apply to assemblage of various subsystems within the
facility and include system design and engineering, assemblage costs, and system
integration costs. Finally,
facility soft costs are those applicable to the entire project including project
management, interest during construction, permitting costs, project design and
engineering, training, debugging and commissioning, and acceptance costs. A reputable
valuation consulting firm can assist in the determination and collection of
these includable costs.
Determination
of Fair Market Value
The determination of fair market
value requires additional judgment and nuance. An appraisal performed under the Uniform Standards of Professional Appraisal Practice of the
Appraisal Foundation requires that the three approaches to value - cost, income,
and market - be considered.
The
reality of the situation is that there will not always be sufficient information
to develop values reflecting all three approaches. In addition, the values that can be
developed under the different approaches will not always be deemed equally
reliable. Finally, those values
will rarely converge to exactly the same figure, and as such, will need to be
reconciled. The reconciliation
process consists of calculating the weighted average of the two or three values
developed; it requires the valuer’s judgment regarding the quality of
information available and the applicability of the results of each approach to
the project under consideration.
(If the available data are such that only one
of the three approaches is deemed reliable, then no reconciliation is
necessary.)
The Cost Approach
The foundation of the cost
approach is the proposition that an informed purchaser would pay no more for
property than the cost of producing a substitute property with the same
utility. When this approach is
applied, facts concerning the property in question are assembled in an appraisal
inventory, and data regarding costs and price-governing factors are
gathered. The accumulated
data are then employed to develop the cost of reproduction new or the cost of
replacement of the subject property.
In the
case of a new renewable energy project, the hard and soft costs described above
would provide a starting point.
However, in considering the cost to a typical market participant,
which in the power generation market would be an operator but not
necessarily a constructor of such projects, one must also consider the
entrepreneurial profit component of the purchase price of a generation
asset. From the constructor’s
perspective, without a profit margin there would be no incentive to build the
project the operator wants to buy.
From a buyer/operator’s perspective, purchasing a complete project means
avoiding the risks of construction, the diversion of a management team whose
skills may not include engineering and construction, and the opportunity cost
(cost avoided by purchasing an existing facility rather than forgoing revenue
during a potentially lengthy permitting and construction period.) In the cost approach, this concept is
reflected by including entrepreneurial profit in the cost buildup. The percentage these potential costs
could add beyond the initial cost will vary from project to project and will
depend on such factors as demographics, permitting time, project construction
period, and market demand.
The Income
Approach
The income approach establishes
the value of the property on the basis of the capitalization of the net earnings
or cash flows expected from the property.
These expected future cash flows are projected over an appropriate time
frame and then converted to present value using a discount rate that reflects
the risks inherent in ownership of the property. The sum of the discounted cash flows
generated by the property provides an indication of its value.
The
income approach to value provides a “ceiling” value (at least in non-speculative
markets) in that a financial investor will not pay more for an asset than the
present value of the income stream it will generate, discounted at the
investor’s hurdle rate. The hurdle
rate should reflect the investor’s cost of funds, the riskiness of the project
and its forecast income stream. The
income stream is typically analyzed on an unlevered basis – the project is
valued as an operating business without consideration of financing.
In
the case of renewable energy projects, while capital costs and operating costs
may be known, revenues may depend on inherently variable volume inputs including
sunshine and wind, as well as variable price inputs, to the extent that
long-term, fixed-price power purchase agreements are not in place. Further, discount rates will vary not only with the investor’s underlying
cost of capital, but the investor’s risk-adjusted return requirements; this may
reflect factors ranging from the scarcity of investment capital, to commodity
price volatility, and to the perceived riskiness of different generation
technologies.
The relationship between the
cost and income approaches is demonstrated in the capital budgeting process, in
which the net present value of an income generating project is determined by
subtracting the project’s acquisition cost from the present value of the income
generated by its operation.
For
clarification, it should be noted that in a sale/leaseback, lease rentals are
not included in the valuation analysis; doing so would permit a circular process
whereby a lessor would be willing to pay whatever purchase price would generate
an acceptable return based on the rentals negotiated with the lessee, regardless
of the underlying profitability of the leased project. While such an arrangement could make economic sense to the lessor if the
lessee were considered creditworthy, it would not reflect the operating
economics, or value, of the project itself, and as such would be an
inappropriate determinant of the project’s tax basis.
The Market
Approach
The market approach establishes
value through analysis of recent sales of comparable property. An analysis is made of the differences
between the properties and the subject, and the sales prices are correspondingly
adjusted to arrive at indications of the subject’s value.
As a general rule of valuation,
the most important determinant of value is actual market transactions. However, depending on the type of asset
being valued, available market transactions for non-commodity assets may not
necessarily be strictly comparable; they may not reliably indicate the value of
the asset under consideration.
Certainly anyone who has ever bought or sold a home is familiar with the
concept of “comps” that are not really comparable to the subject property, and
specialized assets such as renewable energy projects may have significant
differences in size, technology, location, power contracts, weather conditions,
available tax incentives, etc.
While general comparisons of capital cost per kilowatt may provide useful
rules of thumb, the unique features of generation assets are such that, more
often than not, the market approach is not included in the reconciled fair
market value determination of a renewable power project.
Reconciliation of
Value
In determining the final opinion of the fair market value
of a project, the indications of value produced by applying the cost approach,
market approach, and the income approach must be considered.
These approaches to value have
varying degrees of applicability depending on the specific situation. For example, the cost approach is
usually relied upon primarily in situations where the assets are new or nearly
new and fully utilized for their designed intent. The market approach is the most accurate
approach for indicating fair market value as long as there are sufficient
comparable sales of which all the specifics to the various transactions are
known. The income approach would
typically be given more weight if the appraised property had a proven
income-generating history over a sufficient interval so that clear operating
patterns, reflecting a mature operation, could be observed.
The applicability of each approach will
vary for different valuations, and is subject to the appraiser’s level of comfort
with the information provided by each approach, as well as the level of confidence
and supportability in the conclusions derived there from. The final reconciliation may result in a
single approach being selected and supported by the other two, an equal
weighting of all approaches, or an infinite variety of combinations in
between.
Conclusion
The American Recovery and Reinvestment Act of 2009 provides
significant incentives for the development of renewable energy projects, and is
expected to facilitate the financing of many projects that would not otherwise
have been feasible in the current economic environment.
The alternatives offered under
ARRA, such as investment credits vs. production credits, or the option to take
cash grants in lieu of tax credits, support a broad range of potential financial
structures for these projects. As
such, a careful analysis of alternatives is required to determine the optimum
financial structure for a specific project under a given set of market
conditions.
One of the fundamental components
of this analysis is the determination of potential tax benefits of entering into
a lease or partnership structure as an alternative to retaining ownership of a
self-constructed renewable energy project.
The ability to achieve a step-up in basis, from cost of construction to
fair market value, can offer significant economic incentives.
The determination of fair market
value by an independent valuation consultant is frequently used to establish
basis, set purchase options, and confirm compliance with revenue procedures
applicable to tax-oriented financing vehicles. Professional valuation consultants must
be knowledgeable about both asset classes and transaction structures, and must
be able to communicate effectively with financiers, attorneys, and other
professionals and transaction participants in order to assure not only a smooth
appraisal process, but an optimally structured
transaction.